Skip navigation

Community Visitors Banner

Neighbors

Construction and Events

Throughout the year, events and construction projects are happening on and around the University of Denver campus that may impact day-to-day life in the surrounding neighborhoods. Use this list to help anticipate traffic changes, high volumes of visitors to campus or parking challenges.

recent campus events 

Photos from the Hockey National Championship Celebration  

Photos from the Korbel Dinner featuring keynote speaker, Vice President Joseph Biden. Honoring Carrie and John Morgridge of the Morgridge Family Foundation, as well as Kent Thiry of DaVita.

Photos from the Crimson Classic 2016

University of Denver Mobile site

 

upcoming campus events 

 

construction updates

STEM Ponds photo by Wayne Armstrong

 

 

  • Administrative Office Building - 2601 E Colorado Avenue, under construction 2017:

Adminiistrative Office Building

 

Site prep has started the week of April 10th, 2017 and will continue through the end of the month. Truck traffic should be expected as we strip and import soil to raise the grade of the overall site.

May-Caisson Drilling will start May 1 and is expected to be completed in 2-3 weeks.  During this period a concrete pump will be on site daily and its expected that we'll have 2-3 concrete trucks on site throughout the day.

Structural concrete will start at the end of May and extend through the month of June. Truck traffic should be limited to a few deliveries to site, with at least 2 days of larger concrete pours expecting to see 4-5 concrete trucks and a pump each day. 

 

  • 2400 S University (non -DU construction) From Valerie Kerns, Senior Aide , City Council District #6 for the week of April 10, 2017:
    • We have been granted a Harvard Street Closure extension for the duration of 3 weeks (till April 21st)  in order to stage and install material and equipment. We will continue the required lane open for the passage of the daily school busses.

    • Lane closures will be on Tuesday the 18th Wednesday the 19th.  Both days  will involve a single north-bound lane on University from 8:30 to 3:30. The concrete pour is tentative but will remain within the lane closure and given time frame. Lane closures for deliveries will take place both days.

    • Two-way traffic will be maintained on University at  all times. Vehicle and pedestrian traffic will be monitored by flaggers. Lane closures during concrete pours will wrap-up upon completion.

    • No utility work scheduled for this week.

    • Hydro mobile scaffold will continue to be constructed on the west side of the jobsite for building exterior shell work, within the fence-line.

    • We're also conducting block work, sheathing and waterproofing activities on the inside of our fence line, on all 4 sides of the project, all 5 days.

      Access to the east side of the building via the alley way will be essential next week, as forklifts will need to be utilized for block work.

    • Questions regarding the 2400 S. University project can be directed to Denver City Council District 6 at 720-337-6666.  Valerie.Kerns@DenverGov.org

 

 

contact

Please reach out with any questions.

Theresa Ahrens, Interim Communications Director

2199 S. University Blvd.
Denver, CO 80208
Phone: 303-871-4778
Email: Theresa.ahrens@du.edu